Street Sealant Work in Sun City: Updated Dec. 7

Dec 7, 2015

Update, Dec. 7: The street sealant work in Sun City has been hampering residential seasonal shopping traffic and local parcel deliveries.  To reduce disruptions, City crews will be finishing the roadways already started and suspending further sealing until after the first of the year. Existing work should be completed by Wednesday, December 9. (See the updated schedule below.)  The sealing will be resumed in January when disruption to residents and crews will be minimized. Notification of the new schedule will be provided after the first of the year.

Below is the schedule for the sealant work, which will happen from 8 a.m. to 5 p.m. each day. Rain may cause changes to the schedule. The attached color-coded map (below) shows the sections that correspond to the dates.

Date: Section on map Neighborhood numbers
Monday, December 7 Section 2 40, 41, 43
Tuesday, December 8 Section 2 41
Wednesday, December 9 Section 2 41

The sealant product, also called a rejuvenator application, seals the pavement and slows the oxidation process, extending the life of the pavement. The sealant treatment helps to defer more costly maintenance work.

Look for warning signs and flaggers who will be stationed throughout the neighborhood to provide residents with directions. The sealant will be applied to one half of the road at a time. Once the first half has dried, the second half of the roadway will be treated.

Each application typically takes 30 minutes to an hour to dry. High humidity may extend the drying time.

Crews will work to minimize disruptions during the sealant application process.

Driveway Access Affected:  A small orange cone will be placed in each driveway to signal that the sealant has been applied on the street and is in the 60-minute drying process. Residents should avoid driving on the freshly-applied sealant until the driveway cones have been removed. Flaggers will be present to give instructions on temporary parking locations while the sealant is drying.

Schedule changes: This schedule could vary due to rain, other weather conditions, equipment failure, or product availability. The City will update this schedule if there are changes.

Questions about this street work should be directed to Georgetown Utility Systems Customer Care at (512) 930-3640.

Street Sealant Sun City map 10-21-15